Acceleration of construction works
Acceleration is the process of speeding up the work of a contractor so that a particular activity, or the project as a whole, can be completed before the date required under the contract.
Generally, it is the client that requires the acceleration of construction work. A client might require that a building is handed over earlier than is set out in the contract or, where the contractor has been allowed an extension of time, may require completion earlier than the revised completion date. This is referred to as 'directed acceleration'.
Where the contractor incurs additional costs as a result of this sort of acceleration, it can result in a claim against the client. Typically, the contractor does not have to prove the works were actually completed more quickly than originally agreed, just that they made a reasonable attempt to do so and that the attempt resulted in additional costs.
Acceleration of the works may also be undertaken by the contractor voluntarily, if, for example, they wish to move on to another project, mitigate inefficiencies and delays that may have been incurred, or to save on costs. They may also be motivated by bonuses awarded for early completion. However, if acceleration is undertaken voluntarily, the contractor will not be able to claim additional costs from the client.
There are several techniques available for accelerating work:
- Working overtime.
- Adding new shifts.
- Providing additional labour.
- Additional supervision.
- Providing additional resources, such as plant and equipment.
- Re-sequencing work activities (also known as project crashing or fast tracking).
- Adopting alternative construction methods, such as off-site manufacturing.
- Changing the design or specification.
- Reducing the scope of the works (for example transferring responsibility for some works from the contractor to the client), and
- Early procurement of key items.
These techniques are likely to result in additional costs and may not guarantee early completion. While the same number of tasks need to be performed, they are condensed into a shorter period, and so are likely to require more resources. In addition, purchasing costs may be higher due to time pressures, incomplete information and the complexity of managing the interfaces between elements. A greater number of variations are also likely than on a traditional contract.
Options such as working overtime typically result in employees being paid at a higher rate (typically 1.5-2 times the regular rate).
Acceleration is also likely to result in additional risks. If resources are focused on critical-path activities, there is the possibility that non-critical-path activities will be affected. Quality, safety and compliance can be affected, and acceleration can result in an overall loss of productivity, perhaps due to tiredness on the part of workers being required to do overtime, or unfamiliarity of the site and the project on the part of additional workers being brought in.
It is recommended that acceleration agreements are prepared prior to the implementation of acceleration measures to clarify the position regarding factors such as cost, reward and risk.
For more information, see Agreement for the acceleration of construction works.
[edit] Related articles on Designing Buildings Wiki
- Activity schedule.
- Agreement for the acceleration of construction works.
- Benchmark
- Critical path method.
- Expidite.
- Extension of time EOT.
- Fast track construction.
- How to prepare a claim for an extension of time.
- Milestones.
- Project benchmarking.
- Project crashing.
- Resource leveling.
- Resource management.
- Scheduling construction activities.
- Time-location chart.
- Time management of construction projects.
- Variations.
Featured articles and news
The benefits of writing articles for your organisation
How to create a profile for your organisation and publish for free.
No Falls Week. The importance of safe working at height
What to expect and what is on offer to avoid accidents.
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
A forward thinking, inclusive global community of members.
From engineered product life-spans, to their extension.
Circular economy in the built environment
A brief description from 2021. Where are we now?
Mental Health Awareness Week with ABS
Architects Benevolent Society programme of activity.
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
May 13-19: Moving more for our mental health.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Electrotechnical excellence, now open for entries.